Timeline Guide
How long an Altadena rebuild actually takes
Every phase, with the county's real review windows, the Unified Permit, and the decisions that add or remove months from your schedule.
The short answer
6 to 8 months for architectural design and permitting, then 10 to 12 months to build, roughly 16 to 20 months from first meeting to move-in. Like-for-like rebuilds and time-saving packages such as Enhaus Collections land at the fast end. Expanded footprints, hillside lots, and septic upgrades push toward the long end.
Timelines are where rebuild conversations get vague, usually because nobody wants to own a number. Here is ours, phase by phase, with the county's published review commitments alongside it so you can see which parts we control and which parts we do not.
See your timeline
Adjust for your project. Like-for-like keeps the original footprint; expanding or adding an ADU adds review and site scope.
The five phases
1. Consultation and site assessment: 2 to 4 weeks
We walk the property, pull permit and assessor records, review your insurance position, and identify the site conditions that will drive both cost and schedule: slope, soil, septic versus sewer, utility status. This is also when we determine whether like-for-like is right for you, which is the single most consequential scheduling decision you will make.
2. Design and engineering: 2 to 4 months
Architecture, structural engineering, Title 24 energy compliance, and fire-hardening detailing developed together. Because Enhaus holds design, engineering, and construction under one contract, constructability review happens continuously rather than as a handoff, which is where most schedule slippage originates on split-contract projects.
3. Permitting and plan check: 2 to 4 months, overlapping design
Submittal through EPIC-LA or the Altadena One-Stop Permit Center. Plan check runs in rounds: county comments, we respond, resubmit. Two rounds is typical; a well-prepared like-for-like set can clear in fewer. This phase overlaps the tail of design, which is why the combined design-and-permitting window is 6 to 8 months rather than the sum of both.
4. Construction: 10 to 12 months
Demolition and site prep, foundation, framing, envelope and roofing, rough MEP, inspections at each stage, insulation and drywall, finishes, cabinetry, and exterior work. Inspection scheduling is the main external dependency; long-lead materials such as windows and clay tile are the main internal one, and we order those early.



Groundbreaking, framing, and envelope, three of the milestones you will see inside the construction phase.
5. Final inspection and certificate of occupancy: 2 to 6 weeks
Final inspections across trades, defensible space verification, and issuance of the certificate of occupancy. Note that defensible space landscaping must be complete before permit final: the county provides a final inspection report demonstrating compliance, and the CO confirms it. See the compliance requirements →
What the county has committed to
These are LA County's published review windows for fire rebuilds. They are commitments on review time once an application is complete, not the whole permitting phase, which includes your response time between rounds.
Review
Committed window
First review, complete application
Within 10 business days
Subsequent reviews
Within 5 business days
Regional Planning, like-for-like initial
Within 2 weeks
Regional Planning, like-for-like recheck
Within 2 weeks
Non-like-for-like applications
Additional review time may be required
The practical risk is not county speed. It is incomplete submittals: missing documents or upload errors restart the clock, which is why we manage submittal rather than leaving it with homeowners.
The Unified Permit
In August 2025, to streamline rebuilding and reduce the number of applications required per project, LA County implemented the Unified Permit. It consolidates previously separate applications into a single rebuild permit process, administered through the Unified Permitting Authority established within the Altadena One-Stop Recovery Permitting Center: a body empowered to make final permitting decisions without routing back through individual departments.
For homeowners, the effect is fewer parallel applications to track and fewer places for a project to stall between agencies.
EPIC-LA and the One-Stop Center
You have two submittal paths, and they are not mutually exclusive.
- EPIC-LA: the county's Electronic Permitting and Inspection portal, open for submittal any time. Requires architectural plans and a completed Supplemental Form. First-time users register before applying.
- Altadena One-Stop Permit Center: 464 W Woodbury Rd, Suite 210, Altadena, CA 91001, (626) 424-6743. Walk-in hours Monday through Friday, 8:00 AM to 4:30 PM, last call for permits at 3:00 PM. Rebuild consultation appointments are available Monday, Wednesday, and Friday mornings. In-person submittal requires plans and an In-Person Application Form.
The One-Stop Center brings Regional Planning, Building and Safety, Fire Department, Public Health, and Geotechnical staff into one place, along with Southern California Edison planners by appointment. Homeowners receive property-specific packets including permit records, assessor records, and property attributes. If you are early and uncertain, start there.
What actually makes it faster
- Rebuild like-for-like where it serves you: Keeping the original footprint qualifies for the expedited track, and like-for-like replacements are not required to meet current Zoning Code, which avoids variance work entirely.
- Start during debris removal: You do not need to wait for debris removal to finish before submitting plans and applying. Overlapping these is the cheapest month you will ever save.
- Consider a time-saving package such as Enhaus Collections. A Collections plan is already resolved, architecture, assemblies, and a curated selection catalog, so the design phase is shorter and the decisions that normally stall a schedule are made before construction starts.
- Order long-lead items early. Windows, clay tile, and custom millwork drive construction schedule more than labor does.
- Keep design and construction under one contract. Split contracts create handoffs, and handoffs create the gaps where months disappear.
Why this matters for you
FF&E is the line item that surprises families most, because it sits outside every per-square-foot figure and lands right when the money is thinnest. Ask us for the breakdown and we will send the categories, what falls inside a construction contract versus outside it, and the allowance ranges we see on Altadena rebuilds at each finish level.
What delays a rebuild once construction starts
Permitting gets most of the attention, and the sections above cover it. On the build side, delays are almost always a capacity problem: whether the contractor holding your contract can actually execute at the scale they signed for.
Lack of early planning and specialist alignment
This is usually described as subcontractors who were never locked in, but the real problem happens earlier: the trades were never planned and aligned before the contract was signed. When that step is skipped, the schedule attached to the contract is a statement of intent. Trades get priced and committed after the fact, in a market where the whole neighborhood is building at once. Every gap between trades is dead time on your lot, and those gaps compound: a framing crew that arrives three weeks late does not delay framing by three weeks, it moves every trade behind it.
Early planning and specialist alignment is an Enhaus specialty. Before a schedule is issued, our field team and every specialist trade, framing, rebar, electrical, masonry, millwork: sit down together over the actual plan set, sequence the work, and agree on dates. The trades meet each other before they meet your lot.

Alignment before groundbreaking. Our field team and specialist trades working the plan set and the field calendar together: sequencing the trades and committing to dates before construction starts, not after.
Whether your prime contractor is funded
A rebuild runs on phased payments. If the prime contractor cannot carry payroll and material between draws, work slows between payments. In the worse case, unpaid subcontractors and suppliers record a mechanic's lien against your property: your title, for someone else's cash-flow problem. It is a fair and direct question to ask any builder: can you carry the phasing on a project this size?
What vetting actually means
"Vetted" is used loosely in this industry. Here is what it should mean, for the prime contractor and for every trade under them.
Review
Committed window
License
Active, current, and the correct classification for the work: verified, not asserted.
Bonding
Bonded, with the bond in force for the duration of your project.
Workers' comp insurance
Active coverage for every crew on your lot. Without it, exposure lands on you.
Capacity for demand
Whether they can take your project on top of their current load, not whether they want it.
Business infrastructure
Project management, scheduling, procurement, and accounting sized for a project of this scale.
Craftsmanship
Verified completed work in the styles and assemblies your home requires.
Workforce
Crews actually available on your dates, not crews that exist in principle.
Financial capacity
Ability to carry phased payments without stopping work, or exposing you to a lien.
Why this matters for your rebuild
New construction has no phase-in period.
Existing homes get up to five years to comply. Building permit applications submitted after the effective date must meet every Zone 0 requirement immediately, which includes Altadena rebuilds still in permitting. If your plans are in plan check now, this is a live design question, not a future maintenance chore.
The Design Roadmap
From loss to coming home
MONTH 0
MONTH 0
MONTH 0
Drawn to scale: segment length is proportional to each phase's typical duration. Permitting overlaps the tail of design, so the five phases total 16 to 18 months rather than the sum of their parts.

01
2–4 weeks
Consultation
We walk the lot, understand your family, and set the vision and budget together.

02
3–4 months
Design
Architecture, interiors, and material selections, custom or semi-custom.

03
2–4 months
Permits
We navigate LA County and Altadena approvals, including fire-rebuild pathways. Submittal starts before design is fully closed out, so these months overlap.

04
10–12 months
Build
Ground-up construction with fire-rated assemblies and weekly progress updates.

04
2–6 weeks
Homecoming
Final walkthrough, warranty, and the keys to a home built to be handed down.
Start Here · Free Rebuild Assessment
Get a real number for your lot.
We walk your property, review your insurance position, and give you a scoped budget and schedule. No cost, no obligation.
Enhaus Design & Build · License #1104705
Licensed, bonded, and insured · 30+ years experience
778 Alameda St, Altadena, CA 91001
Your first call is with a principal: the same person who runs your project.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Keep reading
Guide
Chapter 7A & the new WUI code
What changed January 2026, and the assemblies your rebuild must meet.
Guide
Altadena permit & build timeline
EPIC-LA, the Unified Permit, and how long a rebuild really takes.